We use cookies to show external content, personalize your experience, to be able to offer functions for social media and to analyze access to our website. By doing so, some of the data about your use of our website may be shared with our external partners. Our partners may combine this information with other data that you have provided to them or that they have collected as part of your use of the services.

You can either agree to accept the usage of all those external services and the respective use of cookies or just accept compulsory cookies which are required to ensure the basic functionalities of this website. Regard, that some pages of this website may not be displayed properly when chosing the later option.

Accept all
Accept necessary cookies only
LTE Header images for design purposes
LTE-NewsNews & Blogup-to-date

„Lokshed“ | Update #1 - and in the beginning…2020-08-12 | LTE News, Ressources

„Lokshed“ | Update #1 - and in the beginning…

After a lengthy phase of planning and preparing, LTS Immobilien GmbH (founded by LTE and ÖBB TS for this purpose) was finally able to give the go-ahead for construction.

Stay informed!

Fill in your email address and get regular updates from LTE-group!

Do not fill out these fieldsDo not fill this out:Do not fill this out:Do not fill this out:

In the last weeks, heavy equipment took over the construction site. Starting on August 3rd, reports Matthias Haiböck, representative of who manages the construction progress of the lokshed, “the remaining tracks and the garage were removed and the slope cleared from vegetation.”

 

Clearing | LTE

 

To avoid unwanted surprises, the building site was searched for power lines and water pipes, cut-off and provisorial power supplies installed. In the meantime, other final preparations have also been made so that the "real" construction work can subsequently be started. This included, for example, test digs, to determine soil conditions. Next steps will be altering (digging) the slope and lowering the construction site by half a meter.

 

Simultaneously the progress is recorded in detail by several cameras situated strategically on site. This material will be publish here from now on. And at the end, we plan to present the building process in a time-lapse video.

 

We keep you posted.

 

 


Share this pageLinkedInFacebookTwitterPer E-Mail TeilenPrint

Contact us

Head Office LTE-group

Bahnstraße 51/1
2440 Gramatneusiedl | Austria
T: +43 (0)316 57 20 20-0
F: +43 (0)316 57 20 20-250

info.at(at)LTE-group.eu

© 2024 LTE group